Industrial Area A1, Block 13002
General Inquiries
A piping system is only as reliable as its weakest joint. Even the highest-quality pipes and fittings can develop installation defects – an improperly welded joint, an undertightened fitting, or a hairline stress crack from mishandling. These defects are invisible to the eye, but they can cause catastrophic failures once a system is pressurized and put into service.
Pre-delivery pressure testing is the industry-standard method for verifying that an installed piping system is completely sound before water flows through it. It is not optional – it is the final quality checkpoint that separates a reliable installation from a liability.
Pre-delivery testing is a hydraulic pressure test performed on site, after assembly is complete, but before the system is handed over and put into operation. The standard testing pressure is 1.5 times the system maximum planned operating pressure.
The factor of 1.5x is defined by international standards (it comes from the German standard DIN 1988-2 for drinking-water installations) and serves two purposes: Safety margin verification confirms the system can withstand pressure spikes and surges. Defect exposure ensures weaknesses are found before they cause damage.
Close all isolation valves and ensure all open ends are capped. Any path for water to escape will invalidate the test.
Fill the system slowly with water. Open vent valves at the highest points to allow air to escape. Air trapped in the system can cause misleading pressure readings.
Divide the system into sections and test each section separately. This allows precise identification of any fault location.
Raise the system pressure to 1.5x the maximum operating pressure and hold for 30 minutes.
If Stage 1 is passed, continue to hold pressure for a further 2 hours.
If the pressure drop exceeds the limit, a leak is present. The affected section must be repaired or re-welded, and the test repeated from Stage 1.
Once both stages are successfully completed:
Pre-delivery pressure testing is not a formality – it is a fundamental engineering requirement that protects your project, your client, and your professional reputation. Every Pinoplast PPR-C piping installation should be tested before commissioning using the two-stage protocol described above. Contact us to schedule your pre-delivery test and receive a verified, ready-to-use installation. Read more about how we test on our Quality & Testing page.